The Timeline is your build programme. It shows each task, how long it takes and when it happens. A task and an activity are the same thing in MyBuildHub, so use whichever word suits you.
Create a timeline
- Go to Timeline and click + New Gantt.
- Enter a name and your start date.
- Choose your working days and hours.
- Click Create new project.
Add a phase
Phases are the main stages of your build, such as Design, Planning or Construction.
- Scroll to the bottom of the task list.
- Click + Add Phase.
- Type the phase name and press Enter.
Add a task or activity
You can do this two ways:
- Click + Add Task at the bottom of the task list, type the name and press Enter.
- Or just type the task name straight into the row and press Enter.
To add a task inside a phase, hover over the phase row and click the + icon.
How phases and tasks work together
- Each task or activity sits under a phase.
- The phase bar runs from its first task to its last task.
- The phase dates, duration and % complete update from its tasks.
- Click the arrow next to a phase to show or hide its tasks.
Edit your timeline
- Double click a cell to change a task name, duration, start or end date.
- Drag a bar to move a task to new dates.
- Drag the circle on a bar to another task to link them.
- Hover over a row to open its details or delete it.
View and share
- Click Day, Week, Month or Year to zoom in or out.
- Use Critical Path, Overdue and Filter to focus on what matters.
- Click Export to print or save your timeline.
Tip
- Keep your timeline up to date. Your cash flow is planned around it.