Using MyBuildHub
How do I add a variation?
A variation is a change to the contract, such as extra work or an upgrade.
- Go to Financial → Cost Management and open the provider (click the ⋮ then View).
- Click the Variations tab, then + New Variation.
- Enter the reference number (e.g. VO-01), title, amount and description.
- Set the Status. Use Anticipated until it is agreed.
- Upload any quotes or supporting documents.
- Click Create Variation Order.
Tip
- Anticipated variations are included in your Forecast Final Cost, so you can see the likely total before they are approved.