How do I link tasks in the Timeline?

Linking tasks shows the order work must happen in, e.g. the slab must be done before the frame starts.

Option 1

  1. Tick the boxes next to the tasks, in order.
  2. Click Link. Each task will start after the one before it finishes.

Option 2

  • Drag the circle at the end of a bar onto the next task.

Remove links

  • Tick the tasks and click Unlink.