Using MyBuildHub

How to use the Timeline: add tasks, activities and phases

The Timeline is your build programme. It shows each task, how long it takes and when it happens. A task and an activity are the same thing in MyBuildHub, so use whichever word suits you.

Create a timeline

  1. Go to Timeline and click + New Gantt.
  2. Enter a name and your start date.
  3. Choose your working days and hours.
  4. Click Create new project.

Add a phase

Phases are the main stages of your build, such as Design, Planning or Construction.

  1. Scroll to the bottom of the task list.
  2. Click + Add Phase.
  3. Type the phase name and press Enter.

Add a task or activity

You can do this two ways:

  • Click + Add Task at the bottom of the task list, type the name and press Enter.
  • Or just type the task name straight into the row and press Enter.

To add a task inside a phase, hover over the phase row and click the + icon.

How phases and tasks work together

  • Each task or activity sits under a phase.
  • The phase bar runs from its first task to its last task.
  • The phase dates, duration and % complete update from its tasks.
  • Click the arrow next to a phase to show or hide its tasks.

Edit your timeline

  • Double click a cell to change a task name, duration, start or end date.
  • Drag a bar to move a task to new dates.
  • Drag the circle on a bar to another task to link them.
  • Hover over a row to open its details or delete it.

View and share

  • Click Day, Week, Month or Year to zoom in or out.
  • Use Critical Path, Overdue and Filter to focus on what matters.
  • Click Export to print or save your timeline.

Tip

  • Keep your timeline up to date. Your cash flow is planned around it.