What should I do when rain or a trade delay affects the building programme?

Record the cause and effect of the delay and ask for an updated programme. A builder's right to extra time depends on the contract and applicable law, including any notice requirements; rain or a trade delay is not automatically an entitlement. Check any response deadline and obtain advice if you disagree. Owner-builders should coordinate changed trade and delivery dates and check effects on approvals, insurance and finance.